PMS on the RIGHT TRACK, Eng. El Sayed El Badawi Field visit to New Cargo 36” Offshore Pipeline at El-Hamra Terminal in the presence of WEPCO and PETROMENT CEOs

Eng. El Sayed El Badawi, Chairman and CEO, made a field visit to onshore and offshore sites of New Cargo 36” Offshore Pipeline at El-Hamra Terminal port of Wipco.
In the presence of Eng. Ahmed Al-Shaer, President of Wipco, Dr. Nael Darwish, President of Petroment and Eng. Hisham Abu Zeid, Projects General Manager of PMS.
Eng. Al-Badawi, expressed his contentment with the performance rates of work which was highly efficient and motivated the employees to finish the laying works with the same performance and outstanding productivity.
It is worth mentioning that the company carries out the following activities:

• New Cargo 36” Offshore Pipeline laying with a length of 8.5 km.
• Finished laying 500m onshore pipeline.
• Finished excavation of a 300m trench.
• Finished sea bed preparation additional works and the maintenance of PLEM and SPM.